A full roof replacement on a standard Maidstone semi-detached takes 3–5 working days from scaffold erection to final inspection.

Day 1: Scaffold Erection

Full perimeter scaffold goes up before any roofing work begins — typically half a day. Clear vehicle access for the scaffold lorry. Scaffold remains for the full duration plus approximately 2 working days for removal after completion.

Day 2: Strip and Survey

All existing tiles and felt are stripped to bare rafter — typically 2–4 tonnes of material for a standard semi. We then carry out a full inspection of rafter timbers, wall plates and insulation. Any rotten or damaged timbers are identified and quoted separately at this stage. We report to you before carrying out any additional work.

Day 2–3: Breathable Membrane and Battens

New breathable felt underlay is laid from eaves to ridge. New treated softwood counter-battens and tile battens are fixed at the correct gauge for the specified tile. On Victorian and Edwardian Maidstone properties, rafter feet at the eaves are checked and replaced if necessary.

Day 3–4: Tiling

Tiles are hung from eaves to ridge. A well-organised crew can tile a standard semi in one day on interlocking tiles. Clay plain tile work takes longer due to the double-lap hanging pattern.

Day 4–5: Lead Work, Ridge and Inspection

All chimney flashings, valley linings and soakers are re-leaded in the correct code weight. Ridge and hip tiles are fixed and pointed or dry-ridge-clipped. Final inspection covers every tile, flashing and ridge section. We photograph the completed roof before scaffold comes down.

What to Prepare

Clear vehicle access for scaffold lorry and skip. Clear fragile items from the loft — tiling vibration is significant. Keep pets inside during scaffold erection and removal. We leave the site clean and tidy at the end of every working day. Call 0162 229 6232 or see our roof replacement page.